U.S. Army School System

U.S. Army School System

Fort Campbell Middle School

Owner: U.S. Army
Tennant: U.S. Army School System
Contract Duration: 32 Months
Location: Fort Campbell, KY

Construct Fort Campbell Middle School” includes all construction work for the primary facilities including, but not limited to, remediation and demolition of existing facilities, excavation of existing site, all underground foundations and support services, construction of the building pad, construction of the additions and renovations, and all building appurtenances as indicated on the Construction Documents. Supporting Facilities – Construct Site Improvements and Utilities” includes all construction work for the secondary facilities including, but not limited to, all dirt work outside of the building pad, secondary electric service from the transformer to the building, secondary natural gas service to the facility, all communication utilities and appurtenances, storm drainage, site improvements, parking lot lighting, geotextile separation fabric, concrete, paving, and striping as indicated on the Construction Documents

Medium and High Voltage

Performed EPC type Medium and High Voltage installation for the Sand Plant industry and other industrial facilities. Substation maintenance and annual testing.

*** Drag a table to scroll ***
Transformer Testing Cable Testing Substation Maintenance
Distribution System Design Distribution System Installation Fall of Potential Testing

Plant #1:

Substation transformer sustained Bushing failure, BBES was asked to provide testing services to determine the root-cause of this damage and perform repairs. In addition to the repairs, BBES was asked to perform annual maintenance on the customer owned 15kV Distribution System.

In order to perform the repair of the Substation Transformer the plant would have to be isolated from the local power grid. In doing the option where to shut production down for 4 days or provide secondary power to the plant. BBES provided secondary power and was able to remove the substation transformer from the grid, perform the bushing replacement while also flushing and cleaning the transformer’s oil. As found test found the transformer had a high content of moisture in the Transformer Oil, lower than normal readings on the windings and a fault condition in the systems readings.

As left testing found the transformer to meet manufacture specifications and re-energization was performed 29 hours after isolation.

Plant #2:

Customer experienced multiple Distribution Circuit trips: testing and review determined system was experiencing wild-life interference with system. BBES installed Wild-Life barriers on existing M.V. terminations and eliminated circuit trips eliminating loss of revenue.

Plant #3:

Customer experienced medium voltage failure on cables feeding loadouts. Upon inspection it was learned that the medium voltage cable supplying power to this end of the plant failed. This event occurred on a Friday afternoon around 4:00pm. BBES was able to mobilize temporary power to return the loadouts to use while sourcing the needed material and returned the plant to full power by 1:00 PM Saturday afternoon.